NEW QUESTION 40
Which is NOT a true statement about the Managing a Stage Boundary process?
- A. It is used to create an Exception Plan if requested by the Project Board
- B. It provides a fixed point at which acceptance of the project product is confirmed
- C. It provides sufficient information for the Project Board to review the success of the current stage
- D. It is executed at, or close to, the end of each management stage, except the final one
Answer: B
NEW QUESTION 41
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
- A. Benefits Review Plan
- B. Team Plan
- C. Stage Plan
- D. Project Plan
Answer: C
NEW QUESTION 42
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project.
2.Stakeholders may be internal or external to the corporate organization.
- A. Only 2 is true
- B. Neither 1 or 2 are true
- C. Both 1 and 2 are true
- D. Only 1 is true
Answer: C
NEW QUESTION 43
Which is one of the six aspects of project performance to be managed?
- A. Timescales
- B. Estimate
- C. Work
- D. Efficiency
Answer: A
Explanation:
Reference http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets
NEW QUESTION 44
Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
- A. 3 and 4
- B. 1 and 4
- C. 2 and 3
- D. 1 and 2
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-quality.php
NEW QUESTION 45
Which is a minimum requirement for applying the organization theme?
- A. The frequency of communication to the project's stakeholders must be documented
- B. Each member of the project management team must have a written role description
- C. The roles of the project management team must be combined, wherever possible
- D. The project manager must be appointed from the supplier organization
Answer: A
Explanation:
Explanation
Reference
http://prince2.wiki/Themes#Organization_Theme
NEW QUESTION 46
Which is NOT obtained from a product's Product Description?
- A. The product's quality criteria
- B. The quality method to be used
- C. The development method to be used
- D. Who will approve the product
Answer: C
NEW QUESTION 47
Which product is used by the Project Manager to authorize work?
- A. Stage Plan
- B. Team Plan
- C. Work Package
- D. Product Description
Answer: C
NEW QUESTION 48
Which is a task of product-based planning?
- A. Produce Product Status Accounts
- B. Write the Project Product Description
- C. Identify activities and dependencies
- D. Prepare the Work Packages
Answer: B
NEW QUESTION 49
Which is a purpose of the 'closing a project' process?
- A. To confirm the project has nothing more to deliver
- B. To establish mechanisms to judge whether the project is still viable
- C. To establish mechanisms for forecasting project objectives
- D. To provide the project board with information to judge the success of a stage
Answer: A
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Closing_a_Project#Objective
NEW QUESTION 50
What theme provides the justification for the project?
- A. Progress
- B. Plans
- C. Business Case
- D. Quality
Answer: C
NEW QUESTION 51
Whose approval is needed to replace a Stage Plan with an Exception Plan?
- A. Team Manager
- B. Project Manager
- C. Corporate or programme management
- D. Project Board
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 52
Which is a type of issue?
- A. An off-specification
- B. A scope tolerance
- C. Aproject outcome
- D. An expected dis-benefit
Answer: A
NEW QUESTION 53
Which statement about the Directing a Project process is true?
- A. Begins on completion of the Initiating a Project process
- B. Ensures there are regular progress meetings
- C. Provides a mechanism for the Project Board to assure that there is continued business justification
- D. Covers the day-to-day activities of the Project Manager
Answer: C
NEW QUESTION 54
Which is NOT one of the levels of plan recommended by PRINCE2?
- A. Stage Plan
- B. Team Plan
- C. Benefits Review Plan
- D. Project Plan
Answer: C