Low investment and high return
Different from general education training software, our Construction-Manager exam questions just need students to spend 20 to 30 hours practicing on the platform which provides simulation problems, can let them have the confidence to pass the Construction-Manager exam, so little time great convenience for some workers, how efficiency it is. Time is money, in today's increasingly pay attention to efficiency, we should use time in the right place, with low time get high scores in return, the Construction-Manager latest exam torrents are very good to do this.
Everybody should recognize the valuable of our life; we can't waste our time, so you need a good way to help you get your goals straightly. Of course, our Construction-Manager latest exam torrents are your best choice. I promise you that you can learn from the Construction-Manager exam questions not only the knowledge of the certificate exam, but also the ways to answer questions quickly and accurately. Now, let me give you a detailed description of the Construction-Manager test torrent. Users can learn from the following three aspects:
Reasonable price with High quality performance
The Construction-Manager latest exam torrents have different classifications for different qualification examinations, which can enable students to choose their own learning mode for themselves according to the actual needs of users. The Construction-Manager exam questions offer a variety of learning modes for users to choose from, which can be used for multiple clients of computers and mobile phones to study online, as well as to print and print data for offline consolidation. Our reasonable price and Construction-Manager latest exam torrents supporting practice perfectly, as well as in the update to facilitate instant upgrade for the users in the first place, compared with other education platform on the market, the Construction-Manager test torrent can be said to have high quality performance, let users spend the least money to meet their maximum needs.
Secure refund guarantee
There are many users who worry that if they fail to pass the exam after purchasing our Construction-Manager latest exam torrents, the money will be wasted, and the cost of the test seems too great to be worth. The Construction-Manager exam questions in order to let users do not have such concerns, solemnly promise all users who purchase the Construction-Manager latest exam torrents, the user after failed in the exam as long as to provide the corresponding certificate and failure scores scanning or screenshots of Construction-Manager exam, we immediately give money refund to the user, and the process is simple, does not require users to wait too long a time. Of course, if you have any other questions, users can contact the customer service of Construction-Manager test torrent online at any time, they will solve questions as soon as possible for the users, let users enjoy the high quality and efficiency refund services.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Time Management | 10% | - Delay Analysis
|
| Contract Administration | 10% | - Contract Types and Structures
|
| Technology | 5% | - Information Management
|
| Cost Management | 10% | - Value Engineering
|
| Safety Management | 10% | - Safety Programs and Policies
|
| Professional Practice | 10% | - Leadership and Communication
|
| Program & Project Management | 20% | - Resource Management
|
| Risk Management | 10% | - Risk Identification and Assessment
|
| Sustainability | 5% | - Green Building Practices
|
| Quality Management | 10% | - Standards Compliance
|
CMAA Certified Construction Manager (CCM) Sample Questions:
1. The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
A) $450,000
B) $270,000
C) $2.7 million
D) $1.2 million
2. When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weatherdelays per year?
A) Ask the contractor to specify the number of weather days they believe necessary for the project.
B) Using a recognized reference such as NOAA. define the number of allowable "normal" weather impact days expected to occur on the project within the contract documents.
C) Defer all issues related to weather to NOAA.
D) Consult a local meteorologist to determine the best estimate of the number of weather days to allow on the project.
3. When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:
A) a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
B) extensive documentation is required to demonstrate sufficient due diligence.
C) contractors only monitor safety if they understand the owner's emphasis on safety.
D) a contractor with a poor safety record is likely to be a low bidder.
4. The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?
A) Advertise the project and award to lowest bidder.
B) Consider the impacts of current market conditions and revise project strategy.
C) Postpone advertising for one year.
D) Market conditions should not be a factor in when a project is advertised.
5. As the owner's representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.
The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor's office. Which entity is best-suited to resolve this risk?
A) Design-Build Team
B) Owner (Municipality)
C) Architect (DOR)
D) Owner's rep
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: B | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: A |